The entire scope of this project was scheduled to be completed within 20 days of shut down period.
KHPT completed this project for 18 days with about 120 local workers, 80 Korean Engineers, Supervisors & Workers.
Revamping Period : Nov.2004 ~ Dec.2004
Subject Works ;
Replacement of Vacuum Transfer Line between the 100¡±/80¡±
(New/Existing) nozzle of the Vacuum column & the 10¡± nozzle of
Vacuum Heater Radiant Coil outlet. Installation of New 100¡± nozzle on the Vacuum Column. Removal of existing 80¡± nozzle & Covering of column shell. Removal of existing Vapour horn & erection of schopentoeter. Replacement of pipe supports, springs, snubbers, sway braces.& etc.