The project required over one years of preparation including elaborated research & planning works for KHPT engineers to overcome the ultimately bad conditions, such as, shortest period,narrowest work area and highest skill-demanding
welding works.
During 52 days of shut down period, with about 350 local
workers, 250 Korean Engineers, Supervisors & Workers,
KHPT conducted this allegedly the biggest and most
complicated revamping work in FCCU plant so far
successfully.